Step by step porting guide and pics 429/460  Same port start to
finish  Each step flow tested
pg 3
click for the big picture
click for the big picture
click for the big picture
click for the big picture
Step 8:
Streamline valve guide boss.
Don't raise left side at this point.
Raise right side .080". Use
barrel tipped burr to trough
around guide
Flow figures at 28" water corrected

.1"     .2"     .3"     .4"     .5"     .6"

52    97     127      148    161   167
Begine to raise right side roof /
longside at this point. Room
permitting. Finish from exit later
This is called digging out the
trenches on either side of the
guide
click for the big picture
click for the big picture
Step 9:
Lay back exhaust bolt hole bump
to existing right side wall
Flow figures at 28" water corrected

.1"     .2"     .3"     .4"     .5"     .6"      .7"

54      98     129   150    162    169    171
click for the big picture
click for the big picture
click for the big picture
click for the big picture
click for the big picture
click for the big picture
click for the big picture
back to page 2
page 4
home
Step 10:
Remove hook upper right corner
Make right exit wall vertical
and square corner
Flow figures at 28" water corrected

.1"     .2"     .3"     .4"     .5"     .6"      .7"

52     97     129     151    165    171    174